A slightly cooler day on site saw Russell and his team back to finish the screed. Here are a sample of the fibres that are added to the water before it is mixed.
Tuesday, 29 June 2010
Monday, 28 June 2010
Screeding part two
Early this morning our second sand mountain was delivered. A new screeding team arrived to do the ground floor. I hope that these guys will achieve better results than the last ones!
Here is Bob, who is organising out the mixing of the screed. Fibres are added to a tub of water that is mixed with the quick-drying cement. These fibres reduce the likelihood of large cracks appearing by making the screed more flexible. Bob's hat shows how hot it was today; over 30C again.
Russell is in charge and does the levelling out. He is using a laser level to check the screed depth as they start with the corner of the kitchen.
Action Adie, who helps with dispensing the screed, runs to check on something. This time the tube for the screed isn't left to wriggle around the floor as it is tied down to scaffolding boards laid on top of a plastic sheet that is protecting the underfloor heating pipes. For those of you who are wondering, the pipes shouldn't collapse under the screed as they are pressurised with air.
Friday, 25 June 2010
Another quiet day
Thursday, 24 June 2010
The house rests
There is a maze of underfloor heating pipes waiting for screeding downstairs. The board in the doorway is there to create an acoustic barrier so that sound isn't transmitted across the floor. It also reduces the risk of the screed cracking. The screeders upstairs insisted that they didn't need the boards and that they would cut a line into the concrete between the rooms, but that didn't happen.
In addition, they pumped the screed through a large pipe that was like a wild dancing python, in the process it damaged the insulation at the bottom of the stairs and over the hall. My daughter and I spent ages sweeping up the dry screed particles and covering the area with tape. Hooray for duct tape! It was hot, smelly work as the heat from the screed is staying in the well insulated house!
Here is the screed upstairs. The thickness variation is just on the borderline of british standard sr3. I'm still not happy with it, I'm sure it's not up to the standards of most other screeders! While I find a new screeder, the project is being held up. Mind you, it gives the screed upstairs a chance to cure undisturbed.
Wednesday, 23 June 2010
Watching screed dry...
This morning the screed upstairs did not look too good. The screeder said it was the quality of the sand and that it was level. I discovered that there is a British Standard in screeding. Apparently over a 2m straight edge there can be a tolerance of +/- 7mm (called SR3). A flowing screed can achieve a slightly higher tolerance apparently. Anyway, I called a halt to the downstairs screeding while I decide what to do.
Meanwhile, the screed upstairs is drying, giving off heat on one of the hottest days of the year.
Meanwhile, the screed upstairs is drying, giving off heat on one of the hottest days of the year.
Tuesday, 22 June 2010
Insulation and Screed
The house is starting to look very smart on the outside meanwhile, on the inside there is a huge amount of activity.
It is all systems go upstairs as we get the floor prepared for the screed. Ebi and Charlie worked all hours to get the insulation ready. Everyone leant a hand to get the tape on the insulation joints at the last moment.
This is then levelled. Unfortunately, the screed mix was a bit rough so a smooth finish wasn't achieved. Hmm, the level doesn't look quite right; it will need to be checked when it's set.
Monday, 21 June 2010
Connections and Insulation
There has been a lot of progress. Here is the cute digger back again that dug the trenches for our water and electricity connections with the help of Jerry and Doru.
Here is the trench that goes from the temporary power supply to the new meter position in our house.
Jerry and Doru apply more layers of black jack on the outside of the floorslab for waterproofing. Insulation is then stuck onto the perimeter of the slab.
The downpipes from the house are now all connected to the drains, ready for the rainwater collection. All the groundworks are now finished so a BIG thank you goes to James, Jerry, Doru and Andy who all got the job done!
The electrical as well as the plumbing connections with the rainwater tank and made. The pump is made ready. Here Matt is pulling the piping through while Josh is at the other end in the house and Neil is shouting directions between them! Good teamwork!
Ebi and Charlie have been working hard, as always. Here is the new position of the foul vent pipe that is in the process of getting boxed in. Unfortunately, they need to do the more imminent job of finishing laying the insulation so that the plumbers can finish installing the underfloor heating pipes and so that we can be ready for the screed tomorrow!
Eventually, long after lunch the delivery comes with a loud cheer. Suddenly, everyone is rushing, the insulation has to go down!
There are so many sheets that they can only just fit on the site. The race is on to see how far they get before the screeding starts. Can the plumbers still lay the pipes if the screeders are going past with screed? There are lots of questions that will need to be answered. Tomorrow we will find out.
Friday, 18 June 2010
Insulation and underfloor heating day 1
The ventilation first fix is finished soon after Adam arrives with the extra ducting. It looks very technical, it's almost a shame that it will be covered by the floor.
But today is really the first insulation day. Here Ebi and Charlie are deciding how to cut the first piece, or maybe it's just a ploy to hide from the camera...
After the whole of the sitting/dining/kitchen has been covered by a layer of insulation, it is sealed and a second layer of insulation is placed on top. Joss is giving Ebi a hand while Charlie cuts the next piece.
So the day ends with grotty weather but we are all feeling light-hearted; England are going to play in the world cup and its friday!
Subscribe to:
Posts (Atom)